Receiving Remaining Assets (Second Method)
When PO is partially received, the balance can be received later through the Item Receipt module.
✅ Steps
Go to Item Receipt Module
Navigate: Purchase → Item Receipt → Create New.
All Approved POs with pending quantities will appear here.
Select PO Number
Choose the PO you are receiving against.
System shows:
Ordered Qty = 5
Received Earlier = 2
Pending = 3
Enter Receipt Details
Example: Receive 2 more laptops now.
Pending reduces to 1.
Ensure Issue Stock = No (since this is an asset, not consumable inventory).
Enter/verify other details → then click Add.
System Processing
Item Receipt created.
Ledger postings done:
Debit: Asset Account linked to Asset
Credit: Purchase Expense Clearing Ledger
Auto Asset Creation
System auto-generates two new asset records with unique asset codes.
Asset Master now shows total 4 Lenovo Laptops (from earlier 2 + 2 new).
You can edit/update the asset codes manually (e.g., FA-00441, FA-00442).
Optionally, can be automated to continue the next sequence number.
✅ Outcome
Assets now tracked individually.
Total purchased = 5.
Total received so far = 4.
Pending = 1 (can be received later).
? Next step in cycle (once all 5 are received) would be to match the Vendor Invoice with PO & Receipts, and then settle payment.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article